Canadian LNG project in Oregon faces delay for regulatory approvals

A Calgary company proposing to build a $10-billion LNG export facility in Oregon says the project timeline is being delayed by about a year.

Reduced level of work is expected to result in construction setback

​Pembina Pipeline Corp. inherited the project when it purchased Veresen Inc. in 2017. (​Pembina Pipeline Corp.)

A Calgary company proposing to build an LNG export facility in Oregon says the timeline for the project — worth an estimated $10 billion US — is being delayed by about a year.

Pembina Pipeline Corp. says it has decided to minimize project spending at about $50 million this year as it tries to vault remaining regulatory and permitting hurdles for the Jordan Cove liquefied natural gas project at Coos Bay, Ore., and a related 370-kilometre pipeline.

The reduced level of work is expected to result in construction delays such that first gas exports are now expected one year later than the targeted date in 2024.

Pembina, which inherited the project when it purchased Veresen Inc. in 2017, said it received a draft environmental impact statement from the U.S. Federal Energy Regulatory Commission in March that provided a framework for approval of the Jordan Cove project as proposed with "reasonable" conditions.

However, a final FERC decision is not expected until next January, and critical Oregon state permits aren't expected until near the end of this year.

A previous, smaller version of the project was denied by FERC in 2016 due to landowner objections and what it said was a failure to demonstrate demand for its product.

Pembina says it still intends to bring in partners for the pipeline and liquefaction facility to reduce its ownership to between 40 and 60 per cent.

It said it has non-binding off-take agreements with customers in excess of the planned design capacity of 7.5 million tonnes per year but will pause executing binding deals until early 2020.
 

Comments

To encourage thoughtful and respectful conversations, first and last names will appear with each submission to CBC/Radio-Canada's online communities (except in children and youth-oriented communities). Pseudonyms will no longer be permitted.

By submitting a comment, you accept that CBC has the right to reproduce and publish that comment in whole or in part, in any manner CBC chooses. Please note that CBC does not endorse the opinions expressed in comments. Comments on this story are moderated according to our Submission Guidelines. Comments are welcome while open. We reserve the right to close comments at any time.

Become a CBC Member

Join the conversation  Create account

Already have an account?

now