Officials in Windsor, Ont., demonstrated a lack of awareness or complete misunderstanding of some of the most basic principles of the laws governing the city when it oversaw the construction of one of its downtown buildings, an audit report has found.
Andrew Roman is the Toronto lawyer who wrote the audit report studying the construction of the 400 City Hall Square building in Windsor, Ont. (Dennis Porter/CBC)The audit report, which was released at a special council meeting on Monday night, said officials were wrong to allow a contractor to amend his bid for the construction project after the deadline for proposals had passed.
Three city councillors who sat on the request-for-proposals committee breached basic rules when they encouraged Windsor-based Vindella Enterprises Inc. to change its bid, ultimately edging out Mississauga-based EllisDon Corporation to win the project.
'Legal is going to increasingly play a bigger role.'—Coun. Fulvio Valentinis
Doing so exposed the city to major risk of litigation, the report concluded. It did not name the three councillors.
The report did not find any sign of criminal wrongdoing, however.
"No evidence that there was misappropriation of funds," said Andrew Roman, the Toronto lawyer hired by the city's audit committee to write the report. "No evidence that there was anything improper done by anyone."
Change necessary
But it made clear that the city administrators cannot continue to operate as they had.
"One of the big recommendations in the report is ... the independence of the solicitor, so he can go right to council to raise these flags, so we don't keep barging on and putting oursel[ves] at significant risk," said Coun. Alan Halberstadt.
"Legal is going to increasingly play a bigger and bigger role," said Coun. Fulvio Valentinis, who chaired the project's steering committee in 2003.
Mayor Eddie Francis said changes have already been made to procedures for future project, but cautioned "there will continue to be room for improvement."
The city's audit committee commissioned the two-part report in 2006 to study the construction of 400 City Hall Square, which houses eight city departments including social service.
Construction began in 2003 with a projected cost of $23 million. After council-approved changes, the final cost ballooned to $32 million. The audit report itself took three years and $600,000 to produce.
Part one of the report was released in February and made 19 recommendations for increased transparency, accountability and better control in future building projects.
Share Tools
Latest Windsor News Headlines
- CAW wants Detroit 3 to invest in Canada
- The CAW says new investment in Canada will be the key issue in upcoming contract negotiations with the Detroit Three. more »
- CP Railway strike halts some international trade
- The waiting games continues for Windsor area businesses that rely partly or wholly on the Canadian Pacific Railway lines. more »
- Windsor told to stick with green energy industry
- A consortium of unions and environmentalists say Windsor still has a chance at being a leader in the green energy manufacturing sector. more »
- Canada ending 'Buffalo shuffle' for visas, closing consulate
- The federal government is shutting the Canadian consulate in Buffalo less than two years after costly renovations, while dropping a requirement for visas to be renewed outside the country, CBC News has learned. more »
Top News Headlines
- Teen struck by lightning in Ottawa dies
- The victim of a Friday lightning strike during a storm in east Ottawa has died, CBC News has learned. more »
- Montreal protesters march in peaceful defiance
- The clanging of pots and pans sounded throughout Montreal's downtown core Saturday night and into early Sunday morning, as thousands of protesters marched on in peaceful — but loud — defiance of Bill 78. more »
- Syrian children massacred by the dozens, UN says
- More than 90 people have been killed by regime forces in a district of central Syria, with the head of the UN team in the country confirming at least 32 children and 60 adults were killed in an artillery attack. more »
- Missing Winnipeg children found in Mexico
- Two Winnipeg children reported missing and possibly in Mexico have been found alive, according to unofficial reports from an agency that works to find missing people. more »
- CP Railway strike halts some international trade
- CAW wants Detroit 3 to invest in Canada
- Teamsters trying to organize parkway truckers
- LCBO now selling more local wine
- Jiimaan to make final trip to Pelee Island before repairs
- Burned out Dollarama unsafe for fire investigators
- Cancer-killing dandelion tea gets $157K research grant
- Trucker protest halts $1.4B parkway project
- Caesars Windsor has 'defence plan' for competition