Regina's 'Big Dig': 10 years on

Here are some of the top stories CBC News prepared looking at the historic 'Big Dig' of Wascana Lake in Regina.

A look back at the big plan to deepen Wascana Lake

Some 96,000 truckloads of dirt were removed during the 'big dig'. (CBC)

Friday marks the tenth anniversary of Regina's "Big Dig": the earth-moving project meant to deepen Wascana Lake.

After letting the water out, crews excavated over one million cubic metres of muck from Wascana Lake. Work started on Jan. 6, 2004 and wrapped up on March 21.

When the project was first pitched it was reportedly going to cost $3 million although other estimates suggested it could cost as much as $12 million. When it was completed, the project cost $18 million.

The excavation was done by Broda Construction of Prince Albert

Here are three interesting facts about the project:

  • Earth removed: 1.3 million cubic metres.
  • Trips by the trucks: about 96,000.
  • Average lake depth increased from 1.6 metres to 5.5 metres (and more in some spots).

Here are links to some of the stories CBC News prepared about the project.

(*Due to the passage of time, you may notice some formatting and compatibility issues for some of the content)

The grounds around the lake are popular with locals who enjoy the pathways and green space.

Comments

To encourage thoughtful and respectful conversations, first and last names will appear with each submission to CBC/Radio-Canada's online communities (except in children and youth-oriented communities). Pseudonyms will no longer be permitted.

By submitting a comment, you accept that CBC has the right to reproduce and publish that comment in whole or in part, in any manner CBC chooses. Please note that CBC does not endorse the opinions expressed in comments. Comments on this story are moderated according to our Submission Guidelines. Comments are welcome while open. We reserve the right to close comments at any time.