Yukon Energy fights major lawsuit by contractor
Countersuit blames unproductive workers for construction delays

Lawyers for the Yukon Energy Corporation go to court this week in Whitehorse to fight a major lawsuit.
North American Construction, the contractor that installed a new turbine at the Aishihik hydro plant in 2011, claims it's still owed millions of dollars.
The $7-million contract called for the new turbine and generator to be operational by fall of 2011, but court documents filed by both parties show the job was plagued with scheduling changes and delays.
North American Construction says those scheduling changes added almost $4 million to the price of the work.
Yukon Energy denies blame for the delays, citing lost production due to "inefficient" and "unproductive" workers.
Yukon Energy has since launched a counter suit, claiming the contract price should be reduced by at least half a million dollars.
At least a dozen witnesses from the two companies are scheduled to testify.
A deputy judge from Alberta, Justice Gerard Hawco, has scheduled four weeks to hear the evidence.
Comments
To encourage thoughtful and respectful conversations, first and last names will appear with each submission to CBC/Radio-Canada's online communities (except in children and youth-oriented communities). Pseudonyms will no longer be permitted.
By submitting a comment, you accept that CBC has the right to reproduce and publish that comment in whole or in part, in any manner CBC chooses. Please note that CBC does not endorse the opinions expressed in comments. Comments on this story are moderated according to our Submission Guidelines. Comments are welcome while open. We reserve the right to close comments at any time.