Point Lepreau delayed until fall 2012
Last Updated: Thursday, October 14, 2010 | 8:19 PM AT
CBC News
Related
Internal Links
External Links
(Note: CBC does not endorse and is not responsible for the content of external sites - links will open in new window)
IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
The $1.4-billion Point Lepreau Nuclear Generating Station will be delayed until the fall of 2012, NB Power announced on Thursday. (CBC)The $1.4-billion Point Lepreau refurbishment project is now delayed until the fall of 2012, NB Power said Thursday.
The refurbishment of Atlantic Canada's only nuclear reactor is now three years behind schedule.
The latest delay comes as Atomic Energy of Canada Ltd. has decided it will remove all 380 calandria tubes and replace them.
“Although the calandria tube installation work sequence will take longer to complete than previously planned, it is essential that these activities achieve the required quality standard in order to provide safe and reliable operation for the next 25 to 30 years,” Gaëtan Thomas, the president and chief executive officer of NB Power, said in a statement.
Thomas said later that he could not guarantee that the promise of newly elected Premier David Alward to freeze rates for three years was still feasible.
"This is one of the things we said we would look at," Thomas said. "We have to look at the impact of this delay and … do that assessment. We will comment on that later."
Thomas said NB Power would take two weeks to review AECL's new schedule and would make public its findings then.
AECL, the federal nuclear corporation, is now expected to finish its portion of the refurbishment project in May 2012. The project will be turned over to NB Power to complete the remainder of the refurbishment with a target date of fall 2012 for the reactor returning to service.
The delay was first announced by NB Power and AECL after 5 p.m. on Oct. 8, as New Brunswickers were preparing for the holiday long weekend.
Premier Alward said on Oct. 12, the day his government was sworn into office, that he wanted to meet with officials from the federal nuclear corporation.
The project was supposed to be completed in September 2009.
The repeated delays have revolved around the reactor's calandria tubes.
All 380 new tubes were inserted in the reactor between December 2009 and April 2010. But dozens of the tubes flunked air tightness tests after being fused with special inserts designed to hold them in place.
The calandria tubes — made to house smaller nuclear pressure tubes, which in turn contain radioactive nuclear fuel bundles — were the first major pieces of equipment to be installed in the reactor as part of Point Lepreau's much delayed refurbishment.
It is estimated that NB Power spends $1 million a day to purchase replacement fuel for each day the nuclear reactor is delayed.
The former Liberal government had threatened to sue the federal government for some financial relief related to the refurbishment project's cost overruns.
Prime Minister Stephen Harper has repeatedly indicated the federal government would abide by the contractual obligations when it comes to paying for any delays at the reactor.
When AECL and the New Brunswick government announced the refurbishment and retubing contracts in 2005, those new agreements included penalty clauses if the project ran behind schedule.
The penalty clauses do not cover all of the costs associated with the mounting delays. Before the refurbishment project began, NB Power took out insurance to help cover any unexpected costs.
Share Tools
Latest New Brunswick News Headlines
- Man arrested for selling fake bus passes on Kijiji
- Saint John Police are warning about fraud on the online classified site Kijiji regarding the sale of city bus passes. more »
- Glut of Tory bills meant to stifle debate, Liberals allege
- The Alward government has launched a legislative blitz on Wednesday, with cabinet ministers introducing 16 bills four weeks before MLAs hope to break for the summer. more »
- Needed: New approaches to defuse 'suicide contagion' among teens
- Mental health experts say we need to find new ways to refer to and discuss suicide, particularly now that a large medical study has confirmed that teens are more susceptible to the idea if they know a schoolmate who died that way. more »
- Paramedics unable to revive Chinese student, inquest hears
- The two paramedics who responded to the near-drowning of a 17-year-old Chinese student at the Canada Games Aquatic Centre in Saint John in 2011 say they tried their best to resuscitate him, but they couldn't get his heart to beat. more »
Must Watch
Top News Headlines
- Neil Macdonald: Harper no Obama when it comes to dealing with scandals
- Beset by three so-called scandals at the moment, Barack Obama has been meeting his accusers and the press head on, Neil Macdonald writes. The same cannot be said for how Stephen Harper operates. more »
- Court freezes assets in widening SNC-Lavalin probe
- The RCMP are moving to freeze millions of dollars in bank accounts and real estate holdings in Montreal and Florida in their expanding probe into Canadian engineering firm SNC-Lavalin. more »
- Needed: New approaches to defuse 'suicide contagion' among teens
- Mental health experts say we need to find new ways to refer to and discuss suicide, particularly now that a large medical study has confirmed that teens are more susceptible to the idea if they know a schoolmate who died that way. more »
- 2nd suspect in Tim Bosma case in court today on murder charge
- A second man arrested in the death of Tim Bosma, a Hamilton father who disappeared after taking two men on a test drive, is due in court today to face a charge of first-degree murder. more »
- Rothesay woman killed in domestic homicide
- Kent Homes in Bouctouche lands its largest contract
- Vandals spray-paint profanity on CFB Gagetown tank
- Duffy should resign over expense scandal, Tory MP says
- Paramedics unable to revive Chinese student, inquest hears
- Glut of Tory bills meant to stifle debate, Liberals allege
- Sale of Edmundston mill good news, mayor says
- Bathurst council rescinds Sunday shopping bylaw
- Dieppe drivers face long delays