N.B. pressures Ottawa on AECL delays
Energy minister calls AECL's communications 'unacceptable and dysfunctional'
Last Updated: Monday, July 26, 2010 | 9:22 PM AT
CBC News
IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
Federal Natural Resources Minister Christian Paradis is being asked by New Brunswick's energy minister to instruct Atomic Energy of Canada to come up with a new timeline on when the Point Lepreau refurbishment will be completed. (Adrian Wyld/Canadian Press)New Brunswick's energy minister is again demanding a clear timeline from the federal government on when Atomic Energy of Canada Ltd. will finish its share of the $1.4-billion refurbishment project at the Point Lepreau Nuclear Generating Station.
Atlantic Canada's only nuclear power plant is mired in delays and is roughly 18 months behind schedule.
Energy Minister Jack Keir wrote to federal Natural Resources Minister Christian Paradis on Monday criticizing AECL's communication with the province over the delayed nuclear construction project.
"It is unacceptable and dysfunctional that information continues to reach NB Power and its shareholder [the New Brunswick government] through rumours and gossip," Keir wrote.
"I am calling the federal government, as AECL's shareholder, to immediately cause AECL to provide a clear and updated timeline to the people of New Brunswick."
The refurbishment is being done in three phases, with AECL being responsible for the second and most complex part of the project. NB Power was responsible for getting the reactor shut down so AECL could begin its part of the project, and AECL will turn the power plant back over to NB Power so it can restart it.
AECL pledged last fall that it would be complete its share of the Point Lepreau work by October 2010. But that deadline will be missed, and the federal nuclear company is no longer estimating when it will hand the refurbished reactor back to NB Power.
Dale Coffin, a spokesman for AECL, said the federal nuclear agency will have a better idea of when the project will be completed when plans are completed for the installation of calandria tubes, which encase the nuclear fuel bundles when the reactor is operating.
"There is no question that AECL will complete the retubing of the reactor and that Point Lepreau Generating Station will be returned to service for another 30 years," Coffin said in an email.
"In the nuclear business there is no room for trial and error. We need to get it right the first time, and we are doing just that."
The calandria tubes, which are about seven metres in length and 13 centimetres in diameter, penetrate the reactor face in big circular rows. All of the nuclear activity of the reactor occurs inside them.
Calandria tube installation is a three-step process involving inserting the tubes, attaching collars at each end to fasten them in place, and then testing the assembly to ensure the unit is air-tight.
AECL has run into problems, as the seals have not met acceptable standards for tightness. AECL said in a July 21 statement that it had completed 75 per cent of the project, but did not give a timeline for the remainder of the refurbishment.
Lack of communication
In his letter on Monday, Keir said the New Brunswick government did not know until a meeting on Sept. 15, 2009, about the extent of the delays.
CBC News reported on Sept. 2 that the reactor was nine months late. AECL said on Sept. 26 that the reactor was 16 months behind schedule.
The province's energy minister said he's tired of learning about potential problems from sources other than AECL.
"We cannot continue to learn of these delays through the rumour mill," Keir wrote.
"AECL, as the lead contractor on this project, has an obligation to formally and officially advise New Brunswickers what the current timelines are."
This is the world's first refurbishment of a Candu-6 reactor, and AECL had hoped that it would be a model to sell to other countries that had purchased the same reactor.
The refurbishment is intended to extend Point Lepreau's life by 25 to 30 years.
Keir and Premier Shawn Graham have raised the possibility of suing the federal government to recoup the cost overruns associated with the reactor.
Share Tools
Latest New Brunswick News Headlines
- 'Unauthorized' pension change to be reversed
- Saint John's outgoing deputy mayor says an "unauthorized change" to the city's pension plan that would have benefitted the city's top earners if they retired early will be reversed. more »
- Fredericton invites citizens to weigh-in on new bylaw
- The City of Fredericton is inviting citizens to have their say on the municipality's new zoning bylaw. more »
- Workers' EI history to affect claim under new rules
- Human Resources Minister Diane Finley announced details this morning about the government's planned changes to employment insurance that would tighten the rules for Canadians collecting the benefit. more »
- 8 views on EI changes: 'political football' or 'eHarmony'?
- Human Resources Minister Diane Finley released more details of the government's plans for reforming employment insurance Thursday. Here's a sample of the reaction. more »
Top News Headlines
- Quebec faces mounting pressure amid student crisis
- The morning after nearly 700 people were arrested in protests in Montreal and Quebec City, Jean Charest announced he has replaced his top aide with his former right-hand man. more »
- Reclaiming the dead on Mt. Everest

- The difficulty, danger and expense of removing the bodies of climbers who died in Mount Everest's "death zone" mean most of the dead remain on the mountain as a stark reminder to other climbers of the risks. more »
- Conservatives move again to have robocalls suits tossed
- The Conservative Party has filed a second motion to dismiss the robocalls lawsuits filed by the left-leaning Council of Canadians, calling council chairperson Maude Barlow a 'virulent critic' of Prime Minister Stephen Harper who has 'orchestrated' the litigation. more »
- Suspect arrested in decades old N.Y. missing boy case
- A man has been arrested in the 1979 disappearance of a six-year-old New York City boy, in the first arrest ever made in a case that helped give rise to the nation's missing-children movement. more »
- Man dies after assault at house party
- 'Unauthorized' pension change to be reversed
- Workers' EI history to affect claim under new rules
- 300 litres of heavy water spilled at Point Lepreau
- Saint John managers ‘duped’ council, says deputy mayor
- Scrap metal plant sparks noise complaints
- Moose on the loose shot in Fredericton
- Food safety course necessary, trainer says
- Plastic bag fees should be legislated, council says