Point Lepreau work delayed again
Nuclear plant's rebuilding postponed another 2 months
Last Updated: Wednesday, May 26, 2010 | 10:27 PM AT
CBC News
Related
IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
The Point Lepreau nuclear plant has been idle for more than two years. (CBC)Two more months have been added to New Brunswick's Point Lepreau nuclear power plant refurbishment schedule, CBC News has learned.
The latest revision comes because efforts to rebuild the province's nuclear reactor missed another critical deadline last weekend.
The $1.4 billion-refurbishment, which is being handled by the federal Crown corporation Atomic Energy of Canada Ltd., began in the spring of 2008, with the reactor originally scheduled to be back up and running by October 2009.
The latest setback involves the installation of calandria tubes, which are about the size of a small sewer pipe and hold fuel channels, including the nuclear fuel bundles, when the reactor is operating.
Since December, crews have been trying to remotely install 380 new calandria tubes in the plant. It's the first major step in rebuilding the station.
Although AECL set aside a month and a half to do the job, internal reports show it's now budgeted to take at least seven months and that is putting the project even further behind schedule.
Test failure
Crews planned to have the job done last weekend, but CBC News has learned that although all of the tubes were installed, several failed critical air-tightness tests.
The job can't progress until each one passes and that won't likely happen until mid-July.
If they do all pass by July, the job will then be 17 months behind schedule with 30 per cent of AECL's work still ahead of it.
In April, NB Power President Gaetan Thomas called on AECL to speed things up.
He said the Lepreau job is critical to NB Power's financial situation. It's costing New Brunswick an extra $1 million per day to pay for replacement power and other costs while the reactor remains offline.
"The responsibility for the Lepreau completion right now is in the hands of AECL," he said. "We are continuing – the minister, myself, all the team on site – to pressure AECL to complete their section of the work. We're ready to go."
The Point Lepreau nuclear plant has been idle for more than two years.
Share Tools
Latest New Brunswick News Headlines
- Trudeau raises environmental questions over pipeline
- Liberal Leader Justin Trudeau says a proposed west-east pipeline project will not go forward unless it addresses key environmental concerns. more »
- Rothesay man charged with 2nd-degree murder
- Adam Prest, 39, has been charged with second-degree murder in the death of his common-law wife Tanya Shand in Rothesay on Wednesday. more »
- Duffy expense claims reveal more about campaign travel
- Election spending records show additional days Senator Mike Duffy spent on the campaign trail in the 2011 election, including days he told the Senate he was on business, and days on which Deloitte auditors couldn't track him. more »
- Chinese student drowned, pathologist tells inquest
- Drowning was the cause of death of a Chinese student in Saint John two years ago, a coroner's inquest was told on Thursday. more »
Must Watch
Top News Headlines
- Toronto Mayor Rob Ford fires chief of staff
- A week after bombshell allegations that Toronto Mayor Rob ford was videotaped smoking crack, the mayor's chief of staff was fired and Ford is continuing to stonewall reporters. more »
- Federal Court won't remove MPs over robocall allegations
- The Federal Court says it won't throw six MPs out of their seats over allegations of widespread vote suppression through automated robocalls in the 2011 federal election. more »
- Alleged Ford crack video seller not responding to calls
- The journalist who broke the story alleging Toronto Mayor Rob Ford was recorded on video smoking crack cocaine says he may never be able to get his hands on the evidence. more »
- Bridge collapse on Washington interstate drops cars into water
- The Washington State Patrol says the Interstate 5 bridge over the Skagit River at Mount Vernon has collapsed, dumping vehicles and people into the water. more »
- Rothesay man charged with 2nd-degree murder
- Trudeau raises environmental questions over pipeline
- Rothesay woman killed in domestic homicide
- New Brunswick fishermen's funerals draw hundreds
- Man arrested for selling fake bus passes on Kijiji
- Kent Homes in Bouctouche lands its largest contract
- Teen dies after falling from moving vehicle
- Fitch faces new questions over trust fund use
- Vandals spray-paint profanity on CFB Gagetown tank

