IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
Atomic Energy of Canada Ltd. has pushed back its deadline again on when it will complete the installation of 380 calandria tubes at the Point Lepreau nuclear power plant in New Brunswick. (CBC)The $1.4-billion refurbishment of the Point Lepreau nuclear reactor in New Brunswick is continuing to miss deadlines set by Atomic Energy of Canada Ltd., CBC News has learned.
The reactor is scheduled to be restarted next February, 16 months behind schedule, but is facing even more problems.
AECL had planned on installing 380 calandria tubes in the nuclear reactor by the start of February, a deadline that was pushed back until the end of March. Now, the federal nuclear agency has postponed the completion date yet again and set a new target for the end of April.
AECL had expected that installing the tubes, which contain pressure rods that hold uranium fuel bundles, would take about eight weeks, but after 11 weeks the installation is still only 25 per cent complete.
When AECL changed its schedule last fall, it built in a degree of flex time just in case there were further delays.
Calandria tube installation is a three-step process involving inserting the tubes, attaching collars at each end to fasten them in place and then testing the assembly to ensure the unit is air-tight.
Internal reports at Atlantic Canada's only nuclear power plant show less than half of those requiring collars have been installed and even fewer have passed the air-tightness test.
October deadline in place
As of March 10, 191 calandria tubes had been installed and the rest are to be in place by late April, AECL spokesman Dale Coffin said in an email to CBC News.
The agency still intends to have its part of the refurbishment complete by October, Coffin said, in time to hand over the reins to NB Power for the final testing and commissioning before the revamped reactor starts producing power in February 2011.
Inserting the new tubes is the first major step in rebuilding the reactor, which was shut down in March 2008 for what was supposed to be an 18-month refurbishment.
However, dismantling the old reactor took 32 weeks longer than expected as remote-controlled tools continually malfunctioned in the radioactive environment.
Cleaning and inspecting the reactor shell ran another 14 weeks late, with calandria tube installation problems adding to those delays. There are two major jobs left for AECL: fuel channel and lower feeder installation, each originally budgeted to take about two months.
The Point Lepreau reactor generates about 30 per cent of New Brunswick's electricity, and the extended shutdown has resulted in significant cost overruns for the province.
The federal and provincial governments have been locked in a war of words over who should cover the costs of the delays, which the New Brunswick government says are the fault of AECL.
The Point Lepreau project is the world's first refurbishment of a Candu-6 facility, and AECL had hoped it would act as a model process that could be sold to other countries that purchased the same kind of reactor.
Share Tools
Latest New Brunswick News Headlines
- 'Unauthorized' pension change to be reversed
- Saint John's outgoing deputy mayor says an "unauthorized change" to the city's pension plan that would have benefitted the city's top earners if they retired early will be reversed. more »
- Fredericton invites citizens to weigh-in on new bylaw
- The City of Fredericton is inviting citizens to have their say on the municipality's new zoning bylaw. more »
- Workers' EI history to affect claim under new rules
- Human Resources Minister Diane Finley announced details this morning about the government's planned changes to employment insurance that would tighten the rules for Canadians collecting the benefit. more »
- 8 views on EI changes: 'political football' or 'eHarmony'?
- Human Resources Minister Diane Finley released more details of the government's plans for reforming employment insurance Thursday. Here's a sample of the reaction. more »
Top News Headlines
- Quebec faces mounting pressure amid student crisis
- The morning after nearly 700 people were arrested in protests in Montreal and Quebec City, Jean Charest announced he has replaced his top aide with his former right-hand man. more »
- Reclaiming the dead on Mt. Everest

- The difficulty, danger and expense of removing the bodies of climbers who died in Mount Everest's "death zone" mean most of the dead remain on the mountain as a stark reminder to other climbers of the risks. more »
- Conservatives move again to have robocalls suits tossed
- The Conservative Party has filed a second motion to dismiss the robocalls lawsuits filed by the left-leaning Council of Canadians, calling council chairperson Maude Barlow a 'virulent critic' of Prime Minister Stephen Harper who has 'orchestrated' the litigation. more »
- Suspect arrested in decades old N.Y. missing boy case
- A man has been arrested in the 1979 disappearance of a six-year-old New York City boy, in the first arrest ever made in a case that helped give rise to the nation's missing-children movement. more »
- Man dies after assault at house party
- 'Unauthorized' pension change to be reversed
- Workers' EI history to affect claim under new rules
- 300 litres of heavy water spilled at Point Lepreau
- Saint John managers ‘duped’ council, says deputy mayor
- Scrap metal plant sparks noise complaints
- Moose on the loose shot in Fredericton
- Food safety course necessary, trainer says
- Plastic bag fees should be legislated, council says