IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
Atomic Energy of Canada Ltd. has pushed back its deadline again on when it will complete the installation of 380 calandria tubes at the Point Lepreau nuclear power plant in New Brunswick. (CBC)The $1.4-billion refurbishment of the Point Lepreau nuclear reactor in New Brunswick is continuing to miss deadlines set by Atomic Energy of Canada Ltd., CBC News has learned.
The reactor is scheduled to be restarted next February, 16 months behind schedule, but is facing even more problems.
AECL had planned on installing 380 calandria tubes in the nuclear reactor by the start of February, a deadline that was pushed back until the end of March. Now, the federal nuclear agency has postponed the completion date yet again and set a new target for the end of April.
AECL had expected that installing the tubes, which contain pressure rods that hold uranium fuel bundles, would take about eight weeks, but after 11 weeks the installation is still only 25 per cent complete.
When AECL changed its schedule last fall, it built in a degree of flex time just in case there were further delays.
Calandria tube installation is a three-step process involving inserting the tubes, attaching collars at each end to fasten them in place and then testing the assembly to ensure the unit is air-tight.
Internal reports at Atlantic Canada's only nuclear power plant show less than half of those requiring collars have been installed and even fewer have passed the air-tightness test.
October deadline in place
As of March 10, 191 calandria tubes had been installed and the rest are to be in place by late April, AECL spokesman Dale Coffin said in an email to CBC News.
The agency still intends to have its part of the refurbishment complete by October, Coffin said, in time to hand over the reins to NB Power for the final testing and commissioning before the revamped reactor starts producing power in February 2011.
Inserting the new tubes is the first major step in rebuilding the reactor, which was shut down in March 2008 for what was supposed to be an 18-month refurbishment.
However, dismantling the old reactor took 32 weeks longer than expected as remote-controlled tools continually malfunctioned in the radioactive environment.
Cleaning and inspecting the reactor shell ran another 14 weeks late, with calandria tube installation problems adding to those delays. There are two major jobs left for AECL: fuel channel and lower feeder installation, each originally budgeted to take about two months.
The Point Lepreau reactor generates about 30 per cent of New Brunswick's electricity, and the extended shutdown has resulted in significant cost overruns for the province.
The federal and provincial governments have been locked in a war of words over who should cover the costs of the delays, which the New Brunswick government says are the fault of AECL.
The Point Lepreau project is the world's first refurbishment of a Candu-6 facility, and AECL had hoped it would act as a model process that could be sold to other countries that purchased the same kind of reactor.
Share Tools
Latest New Brunswick News Headlines
- East Coast braces for severe weather
- Environment Canada issued weather warnings early Saturday afternoon across much of Atlantic Canada and Quebec. more »
- Moncton seniors denied their pets
- The province has ordered a group of Moncton seniors living in a subsidized housing unit to give up their pets or move out. more »
- Attawapiskat sites not ready for modular homes
- The first two of 22 modular homes promised by the federal government to Attawapiskat are on their way to the remote northern Ontario community, but the minister handling the Aboriginal Affairs portfolio is expressing concern over the "readiness" of the lots. more »
- Society slams transfer of female inmates to youth jail

- The Elizabeth Fry Society is concerned that a decision to move incarcerated women to the Miramichi Youth Centre is not fair because it will cut off the women from their family and friends. more »
Top News Headlines
- Greek parliament set for crucial bailout vote
- Greek lawmakers are poised to begin debate on legislation introducing the severe austerity measures necessary for the country to secure a €130 billion bailout and stave off bankruptcy. more »
- Head of Arab League's Syria observer mission quits
- The Sudanese head of the Arab League's observer mission to Syria has resigned, as the group was to consider a proposal to revive its suspended mission, officials said. more »
- Manitoba trailer fire kills 4
- Four people are dead after an early-morning fire quickly engulfed a residential trailer in Selkirk, Man. more »
- Quebec man charged with killing mother, 2 nieces
- A 35-year-old man has been charged with three counts of first-degree murder in connection with the deaths of his mother and two young nieces in Quebec's Eastern Townships. more »
- East Coast braces for severe weather
- Attawapiskat sites not ready for modular homes
- Moncton seniors denied their pets
- Occupy Fredericton eviction legality questioned
- Snowblower that caused stir on Kijiji sold
- Prohibited driver gets jail for 6th offence
- Thrift store forced out after renovations
- Murder-suicide confirmed in northern N.B. deaths
- Society slams transfer of female inmates to youth jail

