Lepreau refurbishment misses another target
Last Updated: Thursday, February 4, 2010 | 6:26 PM AT
CBC News
Related
IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
Saint John Conservative MP Rodney Weston is calling into question the actual cost of replacement power during the $1.4-billion Point Lepreau refurbishment project. (CBC)The refurbishment of Point Lepreau Nuclear Generating Station, which is already expected to be about 16 months behind schedule, has missed another target date.
And as the $1.4-billion project continues to struggle, a Member of Parliament has challenged the province to take the federal government to court over cost overruns.
Atomic Energy of Canada Ltd. (AECL), the federal Crown corporation in charge of project, was supposed to have 380 new calandria tubes installed in the nuclear reactor this week, according to the latest refurbishment schedule, which was revised last fall.
But the tubes are less than 10 per cent complete and won't be finished until at least March.
'Every contract has a dispute resolution mechanism involved. If there's something outside of that, go to the courts.'—Saint John MP Rodney Weston
AECL built significant flex time into its new schedule, so it's unclear whether the tube installation delay will push the overall project beyond the existing 16 month delay estimate.
About five weeks had been set aside for the tube phase of the project, which started Dec. 19. AECL will now have to install about seven tubes a day in order to finish by the end of March, compared to the one a day it's been averaging.
The tubes are each about seven metres in length and 13 centimetres in diameter. They penetrate the reactor face front to back in circular rows. They contain pressure tubes, which in turn hold the uranium fuel bundles. All of the nuclear activity of the reactor occurs inside them.
Inserting the new tubes is the first major step in rebuilding the reactor, which was shut down in March of 2008 for what was supposed to be an 18-month renovation.
Completion is now slated for late 2010.
NB Power has estimated that replacement fuel for each day the nuclear reactor is not running costs it $1 million.
MP says N.B. should sue
Earlier this week Energy Minister Jack Keir renewed calls for Ottawa to pay for the cost overruns even though the province did not negotiate protections against a major delay in the original contract.
"That's not the responsibility of the provincial government. It's not the responsibility of NB Power. And it's certainly not the responsibility of the ratepayers of the province of New Brunswick," he told reporters on Tuesday.
On Thursday, Saint John MP Rodney Weston said he is also disappointed with AECL. "I'm not really impressed that they come out with a price and they're so far off," he said.
The federal government has no intention of compensating New Brunswick for its losses and the province will have to sue Ottawa if wants any extra money, Weston said.
"Every contract has a dispute resolution mechanism involved. If there's something outside of that, go to the courts."
Weston also questioned the actual cost of replacement power during the refurbishment.
Although NB Power has estimated replacement fuel costs about $1 million a day, Weston said Energy Minister Jack Keir has told him the cost of replacement power could be as low as $10 million a month.
It's irresponsible to throw numbers out without backing them up, said Weston.
"I mean, it makes great headlines, I'll give you that. It makes terrific headlines. And it sensationalizes it," he said.
"So, that's what I'm saying, Go prove it. Go prove what the actual damages are. Prove what the actual costs are and get it resolved that way."
Keir said he doesn't remember telling Weston the replacement cost is lower than $1 million a day. "Not to my knowledge, no," he said.
"I've certainly had discussions with Rodney Weston about Lepreau and that deferral account and how the federal government has to come to the table. I don't know, I certainly don't recall it, and I don't know why I would tell him it was $10 million."
Premier Shawn Graham is threatening legal action against the federal government if it doesn't cover the cost overruns. The New Brunswick government has said AECL is to blame for the delays because of an overly optimistic timeline and not enough advance preparation.
AECL has admitted the original timeline for the project was never realistic.
Atlantic Canada's only nuclear reactor was supposed to be operating again in October 2009. Now it's not expected to generate any electricity until February 2011.
This is the world's first refurbishment of a Candu-6 reactor, and AECL had hoped that it would be a model to sell to other countries that had also purchased the same reactor.
Share Tools
Latest New Brunswick News Headlines
- Armed robbery at Saint John gas bar
- There was an armed robbery at a Saint John, N.B., gas station Friday night. more »
- Cataractes advance to Memorial Cup final by beating Sea Dogs
- Yannick Veilleux broke a tie at 13:14 of the third period as the host Shawinigan Cataractes upset the defending champion Saint John Sea Dogs 7-4 in the semifinal of the Mastercard Memorial Cup on Friday night. more »
- 4 arrests in Elsipogtog drug trafficking case
- Four people are facing charges in connection with a two-month long investigation into prescription drug trafficking on Elsipogtog First Nation. more »
- David Alward worried about EI changes
- Premier David Alward says he's worried proposed changes to employment insurance will hurt seasonal industries in the province, such as fishing, forestry and tourism. more »
Top News Headlines
- Teen struck by lightning in Ottawa dies
- The victim of a Friday lightning strike during a storm in east Ottawa has died, CBC News has learned. more »
- Syrian children massacred by the dozens in attack
- More than 90 people have been killed by regime forces in a district of central Syria, with the head of the UN team in the country confirming at least 32 children and 60 adults were killed the attack. more »
- Missing Winnipeg children found in Mexico, organization says
- Two Winnipeg children reported missing and possibly in Mexico have been found alive, according to unofficial reports from an agency that works to find missing people. more »
- Everest team unable to bring down Toronto woman's body
- Bad weather has hampered the recovery team that is attempting to bring down the body of a Toronto woman who died trying to climb Mt. Everest. more »
- Armed robbery at Saint John gas bar
- 4 arrests in Elsipogtog drug trafficking case
- David Alward worried about EI changes
- Woman robs store in Tracadie-Sheila
- N.B. firefighters warned of lawsuit threat
- Loose dog prevents mail delivery to area residents
- Pension snafu may erode public trust, says Norton
- Main Street reopened to traffic
- Pharmacists get generic drug pricing 'transition period'

