AECL says N.B. reactor delay now 16 months
Last Updated: Saturday, September 26, 2009 | 6:51 PM AT
CBC News
Related
IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
The Point Lepreau Nuclear Generating Station will now be off-line until at least February 2011 after Atomic Energy of Canada Ltd. admitted further delays in its $1.4-billion refurbishment. (CBC)The $1.4-billion refurbishment of Atlantic Canada's only nuclear reactor is now more than a year behind schedule, with the target date for power to be generated again at Point Lepreau, N.B., delayed until February 2011.
New Brunswick Energy Minister Jack Keir said in an interview Saturday that Hugh MacDiarmid, CEO of federal Crown corporation Atomic Energy of Canada Ltd., updated him Thursday about the latest delay.
AECL now expects to hand the refurbished reactor back to NB Power on Oct. 15, 2010. At that point, NB Power will finish the final stages of the massive project, with the goal of generating electricity again by February 2011.
The Point Lepreau reactor was supposed to restart on Oct. 1, 2009. Earlier in September, it was estimated the project was nine months behind.
Keir said AECL is accepting full responsibility for the setback and is now making the refurbishment project its top priority.
"Hugh MacDiarmid said very clearly to us that it is their fault. But it is not about blame at this point, it is about getting the job done," Keir said.
AECL is blaming the delay on an overly optimistic timeline at the start of the project and not enough advance preparation work, Keir said.
"Our argument was this contract was signed on an opportunity for success. And it is clear from what he told us on Thursday is, there was no chance for success," Keir said.
"Hindsight is 20/20: He's looked back and seen what work was put into it, and there was no chance for success."
Opposition reacts
New Brunswick's opposition leader is pointing the finger at NB Power over the delays.
David Alward was a minister when the contract was signed under the previous Conservative government.
NB Power told the government the original deadline of this month was achievable, Alward said Saturday, while attending the PC policy convention in Moncton.
"NB Power made the recommendation that the project going forward did make sense and we had built sufficient buffer into it that it was the best decision."
Alward also accused the Liberals of covering up the delays until recent weeks.
But Liberal cabinet minister Donald Arseneault said rather than criticize, the Tories should come up with a clear energy policy.
"They'd just rather take the issue of because there's an extra cost and delays on the project, they'll jump on that issue," he said.
"But they really have to come forward on really where they stand on energy and where they want to bring the energy file forward."
First Candu-6 refurbishment
This is the world's first refurbishment of a Candu-6 reactor, and AECL had hoped that it would be a model to sell to other countries that had also purchased the same reactor.
New Brunswick Premier Shawn Graham wrote to Prime Minister Stephen Harper earlier this month expressing his concern over the uncertainty regarding the massive project's completion date.
In Graham's letter, he said NB Power turned over its portion of the refurbishment project on schedule to AECL.
The province's former Progressive Conservative government renegotiated the refurbishment contracts with AECL, building in penalties if the project went over budget or was delayed.
Keir said the New Brunswick government will be arguing that AECL's admission of sole responsibility for the delays will absolve provincial taxpayers of any financial liability.
"It is solely their responsibility, therefore there should be no sharing of pain," Keir said.
"That is our argument, and we will make that argument very forcefully to the federal government."
NB Power has estimated that replacement fuel for each day the nuclear reactor is not running costs it $1 million.
Keir said the latest admission from AECL will have an impact on power rates, but he said it is too early to tell how much that could be.
The Crown nuclear corporation has had a tough year. Its reactor at Chalk River, Ont., which produces the major part of the world's supply of radioisotopes for nuclear medicine, went offline in mid-May and has suffered three delays in repairs totalling nine months so far.
Share Tools
Latest New Brunswick News Headlines
- Armed robbery at Saint John gas bar
- There was an armed robbery at a Saint John, N.B., gas station Friday night. more »
- Cataractes advance to Memorial Cup final by beating Sea Dogs
- Yannick Veilleux broke a tie at 13:14 of the third period as the host Shawinigan Cataractes upset the defending champion Saint John Sea Dogs 7-4 in the semifinal of the Mastercard Memorial Cup on Friday night. more »
- 4 arrests in Elsipogtog drug trafficking case
- Four people are facing charges in connection with a two-month long investigation into prescription drug trafficking on Elsipogtog First Nation. more »
- David Alward worried about EI changes
- Premier David Alward says he's worried proposed changes to employment insurance will hurt seasonal industries in the province, such as fishing, forestry and tourism. more »
Top News Headlines
- Teen struck by lightning in Ottawa dies
- The victim of a Friday lightning strike during a storm in east Ottawa has died, CBC News has learned. more »
- Everest team unable to bring down Toronto woman's body
- Bad weather has hampered the recovery team that is attempting to bring down the body of a Toronto woman who died trying to climb Mt. Everest. more »
- 32 Syrian children die in artillery attack, says UN
- More than 90 people have been killed by regime forces in a district of central Syria, with the head of the UN team in the country confirming at least 32 children and 60 adults were killed the attack. more »
- Woman's remains found in hockey bag on Cape Breton river
- Police in Nova Scotia are investigating after a woman's remains were found in a hockey bag floating on a Cape Breton river Friday night. more »
- 4 arrests in Elsipogtog drug trafficking case
- Armed robbery at Saint John gas bar
- David Alward worried about EI changes
- Woman robs store in Tracadie-Sheila
- Loose dog prevents mail delivery to area residents
- Pension snafu may erode public trust, says Norton
- Main Street reopened to traffic
- Pharmacists get generic drug pricing 'transition period'
- Bathurst teen charged with attempted murder