AECL says N.B. reactor delay now 16 months
Last Updated: Saturday, September 26, 2009 | 6:51 PM AT
CBC News
Related
IN DEPTH: Point Lepreau
Internal links
- IN DEPTH: Energy
- N.B. reactor upgrade delayed again
- Lepreau refurbishment misses another target
- N.B. premier threatens to sue Ottawa over Point Lepreau reactor
- AECL says N.B. reactor delay now 16 months
- Graham pressures Harper for Point Lepreau deadline
- AECL showing 'lack of focus' on Point Lepreau: Graham
- Point Lepreau refurbishment 9 months late
- Costly Lepreau nuclear plant refit may extend into 2010: VP
- Removing radioactive tubes causes delay in Point Lepreau overhaul
- AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
- Point Lepreau delays will cost $70M to $90M: NB Power
- More delays in Point Lepreau refurbishment: NB Power
- Point Lepreau refurbishment slipping behind schedule
- 'Pain all around' from turbine fall into harbour: NB Power CEO
- N.B. to refurbish aging nuclear plant
- Ottawa rejects New Brunswick nuke funding
- Rebuilding NB nuclear plant '$1.4 billion question'
- Debate over Lepreau future continues
External links
- NB Power's website
- Point Lepreau refurbishment project website
- DOCUMENT: June 30 Point Lepreau Refurbishment Report
- Atomic Energy of Canada Ltd.'s website
- N.B. government decides to proceed with the Point Lepreau refurbishment project
- DOCUMENT: Robin Jeffrey's 2004 review of the Point Lepreau refurbishment project
The Point Lepreau Nuclear Generating Station will now be off-line until at least February 2011 after Atomic Energy of Canada Ltd. admitted further delays in its $1.4-billion refurbishment. (CBC)The $1.4-billion refurbishment of Atlantic Canada's only nuclear reactor is now more than a year behind schedule, with the target date for power to be generated again at Point Lepreau, N.B., delayed until February 2011.
New Brunswick Energy Minister Jack Keir said in an interview Saturday that Hugh MacDiarmid, CEO of federal Crown corporation Atomic Energy of Canada Ltd., updated him Thursday about the latest delay.
AECL now expects to hand the refurbished reactor back to NB Power on Oct. 15, 2010. At that point, NB Power will finish the final stages of the massive project, with the goal of generating electricity again by February 2011.
The Point Lepreau reactor was supposed to restart on Oct. 1, 2009. Earlier in September, it was estimated the project was nine months behind.
Keir said AECL is accepting full responsibility for the setback and is now making the refurbishment project its top priority.
"Hugh MacDiarmid said very clearly to us that it is their fault. But it is not about blame at this point, it is about getting the job done," Keir said.
AECL is blaming the delay on an overly optimistic timeline at the start of the project and not enough advance preparation work, Keir said.
"Our argument was this contract was signed on an opportunity for success. And it is clear from what he told us on Thursday is, there was no chance for success," Keir said.
"Hindsight is 20/20: He's looked back and seen what work was put into it, and there was no chance for success."
Opposition reacts
New Brunswick's opposition leader is pointing the finger at NB Power over the delays.
David Alward was a minister when the contract was signed under the previous Conservative government.
NB Power told the government the original deadline of this month was achievable, Alward said Saturday, while attending the PC policy convention in Moncton.
"NB Power made the recommendation that the project going forward did make sense and we had built sufficient buffer into it that it was the best decision."
Alward also accused the Liberals of covering up the delays until recent weeks.
But Liberal cabinet minister Donald Arseneault said rather than criticize, the Tories should come up with a clear energy policy.
"They'd just rather take the issue of because there's an extra cost and delays on the project, they'll jump on that issue," he said.
"But they really have to come forward on really where they stand on energy and where they want to bring the energy file forward."
First Candu-6 refurbishment
This is the world's first refurbishment of a Candu-6 reactor, and AECL had hoped that it would be a model to sell to other countries that had also purchased the same reactor.
New Brunswick Premier Shawn Graham wrote to Prime Minister Stephen Harper earlier this month expressing his concern over the uncertainty regarding the massive project's completion date.
In Graham's letter, he said NB Power turned over its portion of the refurbishment project on schedule to AECL.
The province's former Progressive Conservative government renegotiated the refurbishment contracts with AECL, building in penalties if the project went over budget or was delayed.
Keir said the New Brunswick government will be arguing that AECL's admission of sole responsibility for the delays will absolve provincial taxpayers of any financial liability.
"It is solely their responsibility, therefore there should be no sharing of pain," Keir said.
"That is our argument, and we will make that argument very forcefully to the federal government."
NB Power has estimated that replacement fuel for each day the nuclear reactor is not running costs it $1 million.
Keir said the latest admission from AECL will have an impact on power rates, but he said it is too early to tell how much that could be.
The Crown nuclear corporation has had a tough year. Its reactor at Chalk River, Ont., which produces the major part of the world's supply of radioisotopes for nuclear medicine, went offline in mid-May and has suffered three delays in repairs totalling nine months so far.
Share Tools
Latest New Brunswick News Headlines
- Trudeau raises environmental questions over pipeline
- Liberal Leader Justin Trudeau says a proposed west-east pipeline project will not go forward unless it addresses key environmental concerns. more »
- Rothesay man charged with 2nd-degree murder
- Adam Prest, 39, has been charged with second-degree murder in the death of his common-law wife Tanya Shand in Rothesay on Wednesday. more »
- Duffy expense claims reveal more about campaign travel
- Election spending records show additional days Senator Mike Duffy spent on the campaign trail in the 2011 election, including days he told the Senate he was on business, and days on which Deloitte auditors couldn't track him. more »
- Chinese student drowned, pathologist tells inquest
- Drowning was the cause of death of a Chinese student in Saint John two years ago, a coroner's inquest was told on Thursday. more »
Must Watch
Top News Headlines
- Toronto mayor fired chief of staff for telling him to 'go away and get help'
- CBC News has learned the details of what precipitated the firing of Mark Towhey as Toronto Mayor Rob Ford's chief of staff — and it was advice from Towhey that Ford needs to 'get help.' more »
- Federal Court won't remove MPs over robocall allegations
- The Federal Court says it won't throw six MPs out of their seats over allegations of widespread vote suppression through automated robocalls in the 2011 federal election. But Judge Richard Mosley did find that fraud occurred in the election. more »
- Alleged Ford crack video seller not responding to calls
- The journalist who broke the story alleging Toronto Mayor Rob Ford was recorded on video smoking crack cocaine says he may never be able to get his hands on the evidence. more »
- Officials 'optimistic' no deaths in Washington state bridge collapse
- An aging bridge on Washington State's Interstate 5 collapsed Thursday evening, dumping a handful of vehicles and people into a river. more »
- Rothesay man charged with 2nd-degree murder
- Teen dies after falling from moving vehicle
- Trudeau raises environmental questions over pipeline
- New Brunswick fishermen's funerals draw hundreds
- Rothesay woman killed in domestic homicide
- Man arrested for selling fake bus passes on Kijiji
- Chinese student drowned, pathologist tells inquest
- Guards in constant conflict over treatment of Ashley Smith
- Atlantic hurricane season forecast to be busy