AECL paying out $100M for Point Lepreau, Bruce refurbishment delays
Last Updated: Friday, February 13, 2009 | 3:10 PM AT
CBC News
Related
Internal Links
External Links
(Note: CBC does not endorse and is not responsible for the content of external sites - links will open in new window)
Atomic Energy of Canada Ltd. is paying out $100 million in extra costs for delays with nuclear refurbishment projects at Point Lepreau, N.B., and the Bruce plant in Ontario. Delays in the $1.4-billion refurbishment of the Point Lepreau, N.B., nuclear power plant are hitting Canadians in the wallet, according to new documents released by the federal government.
The Treasury Board of Canada reported Thursday that Atomic Energy of Canada Ltd. is paying $100 million to cover the cost associated with delays at two nuclear refurbishment projects. The federal Crown corporation is also running late on the refurbishment of a Candu reactor at the Bruce complex near Lake Huron in Ontario, and now Ottawa is budgeting extra money in its latest batch of supplementary estimates.
It's not clear how much of the $100 million is to cover the Point Lepreau delays and how much is for the Ontario project.
David Hay, the president and chief executive officer of NB Power, has estimated that a four-month delay at Point Lepreau could cost the utility upward of $90 million.
AECL is required to pay penalties to NB Power for any delays at Point Lepreau, which was a key part of the refurbishment agreement in 2005.
Hay said the penalties protect New Brunswickers from higher delay costs.
"My view was I negotiated it on behalf of New Brunswick taxpayers," Hay told reporters on Friday.
"And do they have some element towards federal responsibility? Of course. When we hired AECL, everybody knew that. But we're getting a pretty good share of it."
This is the first Candu-6 reactor refurbishment project, which is expected to extend the life of Atlantic Canada's only nuclear power plant by 25 to 30 years. AECL is hoping to market these refurbishment projects to other Candu-6 reactor facilities around the world.
The Point Lepreau project was supposed to be finished at the end of September, but now it may take until Christmas or later.
Norman Rubin of the Toronto-based environmental group Energy Probe said it's unacceptable to not know how that money will be divided up when taxpayers are footing the bill.
"The sad thing here is that you and I and all of your listeners have signed on ... to cover AECL's penalties and overruns, but we're not allowed to look at the contract that triggers those penalties and costs for overruns," Rubin said.
Rubin said if this happened in a private company, heads would roll.
Share Tools
Latest New Brunswick News Headlines
- Budworm outbreak poses $1B threat to N.B. forests
- Forest scientists are warning a bug that first troubled New Brunswick forests 40 years ago is on the brink of another outbreak. more »
- New potato targets diabetics, dieters
- Potato breeders in New Brunswick are creating a tuber to help diabetics and dieters. more »
- Pension trustee takes stand in defamation suit
- A high-profile lawsuit against a former Saint John city councillor over allegedly defamatory comments he made about the city's pension board continued Wednesday with a former long-time city financial officer and board member on the stand. more »
- Half of Canadians report being bullied as youth
- Half of Canadian adults polled say they were bullied as children or teenagers — and 62 per cent of those bullied say having an adult mentor would have helped them cope. more »
Top News Headlines
- Tories move to curb 'bogus' refugees
- The Conservative government is poised to change the refugee system yet again in an attempt to deter what it considers "bogus" claimants, CBC News has learned. more »
- Children of immigrants challenged at school, home
- By 2016, foreign-born youth and Canadian-born youth from immigrant families will make up a quarter of the country's population, according to predictions by the Canadian Council on Social Development. As their numbers grow, more attention is being paid to their successes and failures. more »
- 2 NDP MPs back final Commons vote to kill gun registry
- Two NDP MPs broke party ranks to vote with the government in the final House of Commons vote on scrapping the long-gun registry. more »
- B.C. house party trial hears from tearful teens
- Two teenagers cried as they testified at the trial of a B.C. woman who was charged after a teen died while her son was hosting a party at her house in 2008. more »
- Bodyguard hired for bully victim in Fredericton
- Police tight-lipped on suspicious hospital death
- Fredericton Police warn of bank scam
- Special needs cats hold Valentine's Day Skype date
- Police ID body found on Kingston Peninsula
- Saint John mulls cutting pension guarantees
- Parking shortage at Moncton Hospital
- CUPE questions Horizon's use of parking funds
- SWN may get frosty reception, says mayor