Hydro-Québec was much further ahead than it admitted in preparations to refurbish the Gentilly-2 nuclear power plant near Trois-Rivières, Que., according to a Radio-Canada report. (Jacques Boissinot/Canadian Press)
Hydro-Québec has already spent hundreds of millions of dollars on equipment for refurbishing the province's sole nuclear power plant, components that will likely have to be sold at a steep loss following the government's decision to cancel the project, CBC's French-language service has learned.
The equipment includes the replacement pressure tubes that would have been used to rebuild the reactor core, as well as components for the generator's turbine and computer systems.
Hydro-Québec has also already built a facility for handling nuclear waste and purchased an air-filtration system from the French nuclear company Areva, sources told Radio-Canada.
Guy Marleau, a professor of nuclear engineering at École Polytechnique in Montreal, said the acquired parts are almost all that is needed to refurbish the Gentilly-2 reactor.
Instead, Hydro-Québec is now looking to sell the equipment — but its prospects are dim. The vast majority of nuclear reactors the world over that use the same components aren't in need of a refit.
"I think it will be a pretty difficult task to resell this equipment and, in the best case, if it's sold, it would certainly be at a loss," Marleau said.
Refurbishment plans well advanced
The province's electricity utility had already disclosed millions of dollars in spending toward refurbishing Gentilly-2 before the project was axed.
Hydro-Québec CEO Thierry Vandal said last spring that money was just for preliminary work, such as safety studies, and "only some advanced equipment."
But the Crown corporation has actually acquired the majority of the important systems laid out in its original refurbishment plan.
The former Liberal provincial government decided in 2008 to rebuild Gentilly-2 at a projected cost of about $2 billion, but stopped work after the Fukushima disaster in Japan in 2011 and in the wake massive cost overruns and delays at New Brunswick's Point Lepreau reactor.
The new Parti Québécois provincial government announced Sept. 11 that the plant would instead close. Hydro-Québec subsequently said that a refurbishment would have cost closer to $4.3 billion and that it simply wasn't economical.
Gentilly-2 has been in commercial operation since 1983, and its operating licence runs out at the end of the year. Refurbishing it would have extended that by up to 30 years.
Share Tools
Latest Montreal News Headlines
- 28 students strip-searched at St-Jérôme high school
- One female student told the TVA network that at one point she was asked to remove her bra. more »
- NDP MP Tyrone Benskin 'truly sorry' for not paying taxes
- NDP MP Tyrone Benskin has apologized for not paying his taxes and promises to pay back everything he owes, but has lost his deputy critic duties as a result of the news. more »
- Dachshunds strut their stuff as UN bosses
- CBC Montreal checked out a dress rehearsal Thursday for Dachshund UN, a Festival TransAmériques show featuring dozens of dogs impersonating members of the United Nations. more »
- Has Montreal's reputation taken a hit?
- "No water, no metro, no mayor, no problem" joke picture making the rounds on social media rings true for some Montrealers. more »
Must Watch
Top News Headlines
- Will Rob Ford's supporters leave Ford Nation?
- The growing controversy over a purported video alleging to show Toronto Mayor Rob Ford smoking crack cocaine may be testing the faith of even his most die-hard supporters. But experts say Ford's policies may trump whatever personal issues he's facing, and that his supporters may rally behind him. more »
- Royal Bank pledges not to outsource jobs for cash savings
- Royal Bank has promised it will never outsource a Canadian job to a foreign worker solely to save money. more »
- Neil Macdonald: How serious is Obama about curbing the drone surge?
- In a key speech this week, the U.S. president set out a host of supposed new safeguards for America's controversial practice of remote-controlled rough justice. But as Neil Macdonald writes, the underlying rationale for drone use has not fundamentally changed. more »
- Making The Mandela Tapes
- Producer Robin Benger describes how he obtained broadcast access to interviews Nelson Mandela recorded in the 1990s. A CBC Radio Ideas program on the Mandela tapes airs May 28. more »
- Toronto Mayor Rob Ford denies using crack cocaine
- The mayor of Canada's largest city told a packed news conference that he doesn't use crack cocaine and isn't a crack addict. more »
Most Viewed/Commented
- 28 students strip-searched at St-Jérôme high school
- Has Montreal's reputation taken a hit?
- Montreal lifts boil-water advisory
- Dachshunds strut their stuff as UN bosses
- NDP MP Tyrone Benskin 'truly sorry' for not paying taxes
- Philanthropist, father of Browns Shoes, dies at 85
- Lobbying saved Montreal's UN aviation agency, Paradis says
- Pierre's picks: 5 don't-miss events in Montreal this weekend
- 1.3 million Montrealers face boil water advisory