Manitoba Hydro released details of its preferred route for the controversial Bipole III high-voltage transmission line on the west side of the province.
The proposed line would begin just northeast of the town of Gillam, at Keewatinoow Converter Station, and run southwest past Thompson before turning directly south at The Pas.
'We believe that we have selected the route with the least impact on the environment and on the communities and residents along the proposed path of the transmission line.'—Manitoba Hydro CEO Bob Brennan
It will continue down the west side of the province, near the Saskatchewan border.
Just north of Duck Mountain Provincial Park, the line will angle southeast towards Portage la Prairie. It loops south of that city before turning east and completing the route just east of Winnipeg at the Riel Converter Station in the Rural Municipality of Springfield.
The line will run 1,400 kilometres and will cost $2 billion to build.
"We believe that we have selected the route with the least impact on the environment and on the communities and residents along the proposed path of the transmission line," said Manitoba Hydro president and CEO Bob Brennan.
"We will again be seeking public input into this preliminary preferred route over the next several months before a final route is submitted as part of our environmental impact statement (EIS) for regulatory approval."
Both the Keewatinoow and Riel converter stations are proposed new facilities that will be built if the Bipole III route is approved.
The 5,000-volt transmission line would be installed along a right-of-way that is 66 metres wide and will come into service in 2017.
The project is required to improve system reliability, to decrease dependency on the existing converter facilities and provide additional opportunity for power exports, said Brennan.
East side route rejected
Hydro has been looking at three potential routes along the west side of the province after a shorter route along the east side of Lake Winnipeg was rejected.
The NDP government in 2007 overruled Hydro's original plan to run the line down the east side of Lake Winnipeg.
A major factor was the protection of a proposed UNESCO World Heritage site in that area.
The site, which the province is still seeking to have declared, contains 40,000 square kilometres of vast boreal forest, rivers, lakes and wetlands spread across the Canadian shield and straddling the Manitoba-Ontario border.
Critics, including the Opposition Conservatives, have said Manitoba Hydro's decision to build the line down the west side of the province's big lakes will cost at least $1 billion more because that route is 50 per cent longer than the eastern route.
In coming up with the three possible western routes, Hydro evaluated at a total of 83 alternatives, rating and comparing them using 28 criteria, including:
- Socio-economic concerns.
- Agriculture.
- Caribou and other wildlife.
- Habitat and fragmentation.
- Vegetation.
- Technical feasibility.
- Aboriginal traditional knowledge.
- Stakeholder group considerations.
- Public input.
- Land use patterns and recreation.
The preferred route being presented has the advantage of having the least impact on agricultural land among the three alternatives by avoiding diagonal cuts across properties.
"It takes out … 37 acres of agricultural land. In that whole route, we thought that was excellent — 37 acres is not very much in building a line this size," said Brennan.
In addition, the route avoids National and Provincial Parks, and First Nation reserve lands.
The Manitoba branch of the Wilderness Committee is pleased with the proposed route.
Spokesman Eric Reder said it cuts through mostly cleared land, where the impact on the environment should be minimal.
Consultations set for September
In September, Manitoba Hydro will begin a series of meetings with municipalities and aboriginal groups and stakeholders. The utility will also host a number of public open houses to present information concerning the preferred route and to obtain public feedback.
In addition, a series of "information centres" will be set up for landowners whose property may be affected by the project. The information centres will provide an opportunity for landowners to discuss the project with Hydro staff and obtain more details.
President and CEO Bob Brennan said Manitoba Hydro won't expropriate any land but will offer fair market value to, in effect, "lease" land for the massive power line.
"Manitoba Hydro will provide a fair and equitable compensation package for landowners affected by the preferred right-of-way," stated a release from the utility.
Hydro has also developed a Community Development Initiative (CDI) to provide an annual payment to communities in the vicinity of the Bipole III facilities.
The expected value of the CDI is estimated at $5 million per year over 10 years.
Further information about the CDI will be available during the consultations, Hydro said in a press release.
Share Tools
Latest Manitoba News Headlines
- Lac du Bonnet woman killed in highway crash
- A 38-year-old mother of four from Lac du Bonnet, Man., has died in a two-vehicle crash near the community on Monday afternoon. more »
- Manitoba wants ER death lawsuit thrown out
- A Manitoba court must decide what to do with a court bid by the province to quash a lawsuit by the family of Brian Sinclair, a homeless man who died after waiting 34 hours in a hospital emergency room in 2008. more »
- Stobbe trial hears from blood-spatter expert
- An RCMP blood-spatter expert testified on Monday at the second-degree murder trial in Winnipeg of Mark Stobbe, who is accused of killing his wife, Beverly Rowbotham. more »
- Blue Bombers lock up QB trio
- The Winnipeg Blue Bombers have locked up their quarterbacking triumvirate with the signing of Alex Brink. more »
Top News Headlines
- HMCS Corner Brook collision damage extensive
- The damage done to HMCS Corner Brook when it hit the ocean floor off B.C.'s coast last summer was more extensive than first reported, CBC News has learned by obtaining exclusive pictures of the submarine. more »
- Mandatory gun sentence struck down by Ontario judge
- An Ontario Superior Court judge has struck down a mandatory minimum sentence for a first offence of possessing a loaded firearm. more »
- UN raises fears of civil war in Syria
- Syrian government forces renewed their assault on the rebellious city of Homs on Tuesday, activists said, as the UN human rights chief raised fears of civil war. more »
- U.S. gets 1st hard look at future China leader
- Washington gets its first hard look Tuesday at Xi Jinping, the man destined to lead China in the coming decade, during which the global powers probably will see their economic ties grow. more »
- Lac du Bonnet woman killed in highway crash
- Woman dies after being hit by vehicle in Winnipeg
- Manitoba jail inmates guilty of 2009 assault
- Manitoba wants ER death lawsuit thrown out
- Manitoba man dies after falling off moving SUV
- Boreal ducks threatened by climate change
- Stobbe trial hears from blood-spatter expert
- Winnipeg homicide victim named
- Blue Bombers lock up QB trio