Manitoba Hydro's decision to build a new transmission line on the west side of the province instead of the east is getting mixed reviews.
Manitoba Hydro's third high-voltage direct current transmission line — called BiPole III — will run west of Lake Manitoba, rather than cutting a shorter route through pristine boreal forest on the east side of Lake Winnipeg, officials announced Tuesday.
The western route is 50 per cent longer and will cost an estimated $400 million more to build. The extra resistance on the longer line will also cause more electricity to be lost, potentially costing Hydro millions more in sales .
But environmentalists have applauded the decision, saying that maintaining the untouched section of boreal forest is worth the cost.
"It's a good deal because of all of the services that Manitobans and Canadians get from intact boreal forest," said Gaile Whelan Enns with Manitoba Wildlands.
"If … you count and value all the ecological services that Manitobans receive and Canadians receive from all the intact waterways and rivers and forest lands on the east side, absolutely we'll get $500 million back in ecological services in no time."
Others aren't so sure the longer line is worth it, noting the extra cost works out to about $500 per Manitoban today, and cost estimates are sure to rise before the line is complete in 2017.
Adrienne Batra, Manitoba director for the Canadian Taxpayers Federation, worries about the risk Manitoba Hydro is taking with public money when potential returns from the transmission line could be decades away.
"Arbitrary decisions that they are making are putting Manitobans — you and I — on the hook for potentially a billion dollars in the future, and someone is going to have to pay for this," Batra said.
Premier Gary Doer brushed off concerns, saying export sales would pay for any additional cost, but Batra says export sales are a long way down the road.
"I have a very hard time believing that within the next 20 years, suddenly Hydro is going to be reaping multi-billion dollars in revenue to be paying off these debts," she said.
The new line will begin at Gillam, in northern Manitoba, run west of Winnipegosis and Lake Manitoba and end at a new converter station east of Winnipeg.
The precise route for the $2-billion line will be determined after an environmental, design and public consultation process that is expected to take several years.
About three-quarters of Manitoba Hydro's electricity production is currently supplied through two transmission lines that run from Gillam to Winnipeg through the Interlake area.
BiPole III will provide a back-up to those lines and carry power from new planned generating stations to southern Manitoba.
Share Tools
Latest Manitoba News Headlines
- Missing boater may have struck reef, police say
- A boater who has been missing since Tuesday may have struck a reef, police say, adding a search for the man is continuing. more »
- Crime spree ends with 46 break-in charges
- Police in Winnipeg think they have caught the person behind a string of early-morning break-ins, where a vehicle was used to smash into businesses. more »
- RCMP to close labs in Halifax, Winnipeg, Regina
- The RCMP is closing forensic laboratories in Halifax, Winnipeg and Regina and consolidating them with three others in a move the force says will lead to faster, more efficient service. more »
- Winnipeg's Union Station to get facelift
- The 100-year-old Union Station in Winnipeg is set to get a $6.5 million facelift. more »
Top News Headlines
- Dozens of children die in Syria massacre, activists say
- More than 90 people have been killed by regime forces in a district of central Syria, activists say, and as many as half the victims may have been children. more »
- Aylmer triple stabbing leads to first-degree murder charges

- The estranged partner of a young mother who was stabbed to death along with her parents at their home in Aylmer, Que., has been charged with first-degree murder Friday. more »
- Severe storm in Quebec leaves damage in its wake
- Trees were uprooted, roofs damaged and windows shattered as severe thunderstorms, and possibly a tornado, rattled through southwestern Quebec Friday night. more »
- The risks and responsibilities of taking on Mt. Everest

- The deaths of five climbers last weekend on Mt. Everest, with more summits underway this weekend, fuels the debate about the risks and responsibilities of high altitude climbing. more »
- Winnipeg WWE wrestler Chris Jericho suspended after flag incident
- Crime spree ends with 46 break-in charges
- Outhouse bear attack survivor was grabbed from 'throne'
- Missing boater may have struck reef, police say
- First-time homebuyers find frustration in Winnipeg
- Kelvin High School celebrates 100 years
- Winnipeg's Union Station to get facelift
- RCMP to close labs in Halifax, Winnipeg, Regina
- MPI asked to cover tab for officers' overtime