TransCanada cleared of Keystone conflict by U.S. audit
U.S. State Department faulted for some aspects of permit review
By Susana Mas, CBC News
Posted: Feb 9, 2012 7:31 AM MT
Last Updated: Feb 10, 2012 10:50 AM MT
Related
Related Stories
External Links
(Note:CBC does not endorse and is not responsible for the content of external links.)
TransCanada has been cleared of any undue influence in the U.S. State Department's decision to hire Cardno Entrix, a client of TransCanada, to conduct an environmental impact review of the $7-billion Keystone XL pipeline project, an audit by the U.S. Inspector General has found.
In a 58-page special review of the Alberta-to-Texas Keystone XL pipeline permit process tabled in Congress Thursday, Inspector General Harold W. Geisel found "no evidence that TransCanada had improperly influenced" the department's decision to hire Cardno Entrix to perform the environmental impact analysis of the proposed Keystone XL pipeline project.
TransCanada's "influence was minimal," and the main factor behind the State Department's decision to hire Cardno Entrix was the department's "previous experiences using the company as a third-party contractor for other environmental impact statements," found Geisel.
Furthermore, Geisel found no evidence to suggest that "communications between U.S. State Department officials, TransCanada, the Canadian government, proponents and opponents of Keystone XL deviated from the department's obligation under federal law" to provide an objective analysis of the project and its potential risks.
Russ Girling, TransCanada president and CEO, welcomed the findings of the review.
"The independent investigation confirms we followed all of the procedures and practices established by the Department of State and other federal agencies," said Girling in a statement on Thursday.
Process for hiring contractor criticized
The Inspector General did find fault with the handling of some aspects of the pipeline permit process by the U.S. State Department itself.
For instance, Geisel acknowledged that the State Department's process to hire a third-party contractor to perform an environmental impact statement "inherently gives the applicant some influence in the process."
The process allows the applicant to decide which contractors receive the requests for proposal, review the proposals, and identify its preferred contractor, Geisel explained in the audit.
To that end, Geisel recommended that the State Department modify its third-party contracting process to "reduce the appearance of improper influence."
Although Geisel did not find "an organizational conflict of interest" between Transcanada and Cardno Entrix, his audit found that the State Department did not request that information from the contractor but rather accepted it "at face value."
Geisel said that omission could call a contractor's "objectivity into question" and recommended the State Department's screening process be "redesigned" and "improved."
Finally, Geisel also had "some concerns' with the way in which alternative routes for the proposed pipeline were considered and "not completely incorporated" in the department's final environmental impact statement.
Geisel determined that the department's "limited technical resources, expertise, and experience impacted the process," and recommended that the department hire extra staff, something the department told Geisel it is currently in the process of doing.
'Shoddy, unscientific review,' says congressman
The Office of the Inspector General was asked to review the pipeline permit process following a complaint by Representative Steve Cohen (a Tennessee Democrat) and Senator Bernie Sanders (a Vermont Independent) on behalf of 11 legislators alleging the environmental review was biased in favour of TransCanada.
After the review was tabled on Thursday, Cohen said the report "undermines the integrity of the project's review and underscores the point that the pipeline should not be approved based on a shoddy, unscientific review."
Sanders said the findings confirmed "why the project should not be rubber-stamped for approval, despite efforts by Republicans in Congress to do just that."
The inspector general interviewed officials and examined documents within at least half a dozen bureaus that were involved in evaluation of TransCanada's Keystone XL pipeline permit.
The Obama administration delayed approval for the Keystone XL pipeline until after the 2012 election. But in December, the Republicans included a Feb. 21, 2012, deadline for the decision in a bill to extend payroll tax cuts.
But last month, U.S. President Barack Obama rejected the proposal for Keystone XL, saying the Republican deadline did not provide enough time to conduct a proper review, and invited TransCanada to reapply for a permit.
On Thursday, Girling maintained that TransCanada is fully committed to the project and will reapply for a permit to build the pipeline, a process TransCanada hopes will be handled in an "expedited fashion" due to the work already completed during the review process.
Girling added that "plans are already underway on a number of fronts to do our part to maintain the project’s construction schedule," and that "shippers continue to tell us that this critical North American energy infrastructure project is needed."
Meanwhile, Republicans in Congress appear undeterred in their resolve to see the proposed Keystone XL pipeline project built, as they continue to push new bills that would require approval of the project.
Share Tools
Latest Calgary News Headlines
- Thousands pack 4th Street for Lilac Festival
- Large crowds hit Fourth Street for the Lilac Festival on Sunday. more »
- Calgary Marathon winner breaks 21-year-old record
- The winner of the Calgary Marathon broke a 21-year-old race record. more »
- Man in hospital after being pinned under C-Train
- A man is recovering in hospital after he was hit by a C-Train and trapped underneath Sunday afternoon. more »
- Canadian Pacific strikers face back-to-work legislation
- Labour Minister Lisa Raitt is prepared to end the Canadian Pacific Railway strike if necessary, after both CP and the union rejected a proposal for voluntary arbitration by the government-appointed negotiator on Sunday. Raitt says she is "extremely disappointed." more »
Top News Headlines
- Canadian Pacific strikers face back-to-work legislation
- Labour Minister Lisa Raitt is prepared to end the Canadian Pacific Railway strike if necessary, after both CP and the union rejected a proposal for voluntary arbitration by the government-appointed negotiator on Sunday. Raitt says she is "extremely disappointed." more »
- Syrian regime denies role in Houla massacre
- The UN Security Council condemned the Syrian regime at an emergency meeting Sunday, holding president Bashar al-Assad's military responsible for the massacre of more than 100 people, dozens of whom were children younger than 10 years old. more »
- Ryder Hesjedal wins prestigious Giro d'Italia
- Victoria native Ryder Hesjedal has become the first Canadian to win one of the cycling world's three Grand Tour events, wrapping up the 2012 Giro d'Italia with an excellent performance in the final stage in Milan. more »
- Neighbour may have helped find missing kids in Mexico
- Two Winnipeg children who had been missing for nearly four years were found in Mexico after a man raised concerns about his neighbour, according to a private investigator. more »
- Accused in blast that killed Alberta mom handled her funds
- Calgary Marathon winner breaks 21-year-old record
- Man in hospital after being pinned under C-Train
- Thousands pack 4th Street for Lilac Festival
- Half the vehicles tested fail new road noise bylaw
- Police ask for help after man found dead in Forest Lawn
- Food festival encourages Calgarians to 'eat real'
- 2 men charged in connection to brutal Beltline beating
- Canadian Pacific strikers face back-to-work legislation