Latest cost overruns may slash social housing in Olympic Village project
Last Updated: Monday, February 16, 2009 | 9:19 PM PT
CBC News
Related
Internal Links
External Links
(Note: CBC does not endorse and is not responsible for the content of external sites - links will open in new window)
Seven hectares of the 32-hectare Southeast False Creek development site will be transformed into the Olympic Village during the 2010 Winter Games. (CBC) About 250 social housing units included as part of the Olympic Village project for the 2010 Winter Games may face the axe due to new cost overruns, according to a Vancouver city administrative report.
The cost of the affordable housing component of the project has risen to an estimated $110 million — a 70 per cent increase over the original budget of $65 million — says the report, released Monday night on the city's website.
Between $56 million and $77 million in additional city equity would be required to sustain affordable housing in the project, the report says.
"Staff must now review a number of options that can be brought to council for a decision related to the plan for delivering on the affordable housing commitment," it says.
The city needs to maintain "careful cost control" to prevent any further cost overruns, it says.
The report says the overruns stem from higher costs for exterior finishes, a tighter construction market, the project's firm deadline and an expansion of the floor area dedicated to affordable housing units.
The report asks the city's managing director of social development to get back to council by April 15 on financial and operational options for the affordable housing component of the Olympic Village.
Series of financial woes
The cost overruns for the affordable housing are the latest in a series of financial woes for the Olympic Village project, which is being built on undeveloped waterfront land in southeast False Creek, near downtown Vancouver.
Last month, the city of Vancouver received the go-ahead to borrow up to $485 million needed to complete the Olympic Village for the 2010 Winter Games after the province passed a bill amending the city's charter.
The city has to deliver the athletes village with 1,100 units of housing by November this year to accommodate up to 2,800 athletes and officials during to the Games, a report last month by city manager Penny Ballem said.
The village was supposed to include what would become, once the Games are over, 250 social housing units, 730 market sales units and 120 rental units.
The city stepped in after the project ran into financial problems. A New York hedge fund was to lend the $750-million budgeted for the construction, but it cut off payments to the developer in September.
Since cash advancements to builder Millennium Development Corp. from Fortress Investment Group stopped, the city had been covering construction costs with a $100-million bailout loan approved during an in-camera council meeting on Oct. 14. That money ran out in mid-January, so Mayor Gregor Robertson asked the province to change the municipality's charter to allow it to borrow to fund all remaining work.
Cost overruns have pushed the project cost to $875 million. The southeast False Creek development site is on city-owned land worth $200 million, putting the value of the whole development project at more than $1 billion.
Share Tools
Latest British Columbia News Headlines
- Ryder Hesjedal wins prestigious Giro d'Italia
- Victoria native Ryder Hesjedal has become the first Canadian to win one of the cycling world's three Grand Tour events, wrapping up the 2012 Giro d'Italia with an excellent performance in the final stage in Milan. more »
- Surrey RCMP seek hit-run driver
- Police are looking for a light-coloured Chrysler with damage to the driver's front side after a pedestrian was hit in Surrey, B.C., early Sunday morning. more »
- B.C. man who scaled Everest returns home
- A Vancouver man who climbed the world's highest mountain is back home and talking about the adventure. more »
- Fort Langley restaurant damaged in fire
- A sushi restaurant in Fort Langley, B.C., was damaged in a fire early Sunday morning. more »
Top News Headlines
- Canadian Pacific strikers face back-to-work legislation
- Labour Minister Lisa Raitt is prepared to end the Canadian Pacific Railway strike if necessary, after both CP and the union rejected a proposal for voluntary arbitration by the government-appointed negotiator on Sunday. Raitt says she is "extremely disappointed." more »
- Syrian regime denies role in Houla massacre
- The UN Security Council condemned the Syrian regime at an emergency meeting Sunday, holding president Bashar al-Assad's military responsible for the massacre of more than 100 people, dozens of whom were children younger than 10 years old. more »
- Ryder Hesjedal wins prestigious Giro d'Italia
- Victoria native Ryder Hesjedal has become the first Canadian to win one of the cycling world's three Grand Tour events, wrapping up the 2012 Giro d'Italia with an excellent performance in the final stage in Milan. more »
- Neighbour may have helped find missing kids in Mexico
- Two Winnipeg children who had been missing for nearly four years were found in Mexico after a man raised concerns about his neighbour, according to a private investigator. more »
- B.C. NDP calls for unity in fighting coast guard closure
- Surrey RCMP seek hit-run driver
- B.C. man who scaled Everest returns home
- Fort Langley restaurant damaged in fire
- Passengers' families sue for fatal B.C. plane crash
- B.C. Coast Guard Auxiliary gets new name
- Tsunami motorcycle heading to Harley museum
- Psych ward escapes worry neighbours
- Gang forum honours Surrey 6 victim