Point Lepreau delay could jeopardize PC promise

Last Updated: Thursday, September 23, 2010 | 5:28 AM ET

The $1.4-billion Point Lepreau refurbishment project is facing more delays and could jeopardize a Tory election promise to freeze power rates.The $1.4-billion Point Lepreau refurbishment project is facing more delays and could jeopardize a Tory election promise to freeze power rates. (CBC)

The $1.4-billion Point Lepreau nuclear refurbishment project is facing another major delay as officials consider removing 380 brand new calandria tubes from the reactor, CBC News has learned.

Kathleen Duguay, a spokesperson with NB Power, said removing all of the tubes and starting the installation again is one of two options being explored by Atomic Energy of Canada Ltd., the federal Crown agency, to get the stalled refurbishment moving.

"A decision on the path forward cannot be made until all technical assessments are complete," Duguay said.

She said starting over is a real possibility, but a decision and announcement on whether to remove all of the newly installed tubes will come shortly after New Brunswick's Sept. 27 provincial election.

PC Leader David Alward says he would freeze NB Power rates for three years even if the Point Lepreau reactor missed its latest restart date.PC Leader David Alward says he would freeze NB Power rates for three years even if the Point Lepreau reactor missed its latest restart date. (CBC)

The Point Lepreau refurbishment debacle has so far not seriously factored as an election issue in New Brunswick since the Progressive Conservatives made the decision to proceed with the refurbishment during their last government with full Liberal support.

However, the latest troubles could be a problem for Tory Leader David Alward, who has promised a three-year freeze on power rates if he's elected.

The freeze was calculated on the assumption the Point Lepreau reactor would be operational by February 2012.

But if AECL takes another year to remove and reinstall the calandria tubes, the target date will be unobtainable.

Alward told CBC News on Thursday that he still believes the rate freeze is viable even if the reactor overshoots party estimates.

"We feel very confident with the recommendation," he said.

Repeated delays

Work at the Point Lepreau refurbishment has been at a near standstill for five months as engineers try figure out what to do with leaky calandria tubes that hold fuel channels, including the nuclear fuel bundles, when the reactor is operating.

The calandria tubes — made to house smaller nuclear pressure tubes, which in turn contain radioactive nuclear fuel bundles — were the first major pieces of equipment to be installed in the reactor as part of Point Lepreau's much delayed refurbishment.

The project is now more than a year behind schedule and hundreds of millions of dollars over budget.

All 380 new tubes were inserted in the reactor between December 2009 and April 2010. But dozens of the tubes flunked air tightness tests after being fused with special inserts designed to hold them in place.

Eighty failures were detected during tests of the tubes, which are attached at both ends for 760 total seals.

AECL finally acknowledged the tubes and their inserts weren't smooth enough to form a consistently tight seal and that polishing the ends would have made them fit tighter.

Eight tubes were removed from the reactor and replaced with newer polished versions and were found to fit much better.

The last of the eight was installed last Friday and all eight have passed inspection.

But replacing all of the tubes would be no small job.

It took AECL a year to remove the original calandria tubes and replace them with those now there. A second problem is that for months now, all of the tubes have been sitting in the reactor, which remains highly radioactive.

Related

Overall Results

Overall Election Results
Party Elected Leading Total
Updated: Sep. 28, 2010, 12:49 AM ADT
PC 42 0 42
LIB 13 0 13
NDP 0 0 0
GRN 0 0 0
PA 0 0 0
IND 0 0 0

Choose a format to view results for all ridings and parties:

All results are unofficial until final ballot counts are verified by Elections New Brunswick.

New Brunswick Votes Headlines

Alward picks ex-PC candidate as chief of staff
Premier-designate David Alward has tapped three-time defeated Bathurst Tory candidate Nancy McKay to be his chief of staff.
Liberals request Saint John Harbour recount
Liberal cabinet minister Ed Doherty has requested a recount into the results of his Saint John Harbour election, which he lost by a mere nine votes on Monday.
N.B. voter turnout lowest since 1978
New Brunswick voters made history on Monday by dumping the first one-term government since Confederation but voter turnout was much lower than expected.
Alward prepares PC transition plan
The Progressive Conservatives are busy preparing for their Oct. 12 return to power as Premier-designate David Alward is naming his transition team and lining up meetings with top bureaucrats.
Bathurst PC candidate requests recount
The Progressive Conservative candidate in the northern riding of Bathurst has decided to ask for a recount after losing the seat by just 75 votes.

My Riding & Riding Talk

Have your say about what's important in your own riding. Read profiles about your candidates, get riding-related information and join the debate.

Find My Riding

List All Ridings

Top CBCNews.ca Headlines

Headlines

Tornado touchdown confirmed near Montreal
Trees were uprooted, roofs damaged and windows shattered as severe thunderstorms, and a tornado rattled through southwestern Quebec Friday night.
Everest team unable to bring down Toronto woman's body
Bad weather has hampered the recovery team that is attempting to bring down the body of a Toronto woman who died trying to climb Mt. Everest.
Attack on Syrian villages deadliest yet, activists say
More than 90 people have been killed by regime forces in a district of central Syria, with the head of the UN team in the country confirming more than 32 children and 60 adults were killed the attack.
Aylmer triple stabbing leads to first-degree murder charges video audio
The estranged partner of a young mother who was stabbed to death along with her parents at their home in Aylmer, Que., has been charged with first-degree murder Friday.
The risks and responsibilities of taking on Mt. Everest video audio
The deaths of six climbers last weekend on Mt. Everest, with more summits underway this weekend, fuels the debate about the risks and responsibilities of high altitude climbing.